HILL FSR M


Who turned the tap on?

  • By David Cooke
  • 06 Sep, 2017

The recent rain is helping fill the marina

We have a meeting with CRT (Canal and River Trust) on Thursday 14th September, we hope, to be able to finalise the canal connection. The recent rain is working in our favour. Don't worry the pontoons will be covered with the latest innovative non slip GRP decking that we have imported from China it will only take us an hour and 36 screws to finish each pontoon.

The start of Hill Farm Marina

By David Cooke 27 Nov, 2017
The farms geese have really enjoyed the development of the marina, we have also attracted other wildlife we often have visits from a loan Swan, Mallard ducks and a single white duck. Fish has also taken residence and have been seen jumping regularly in the new marina basin.
By David Cooke 12 Nov, 2017
It's great to have boats moored after 18 months of building, we have power, light and water, and more boaters on the way before the winter stoppages. Work will still progress over the winter in preparation the majority of our narrow boaters who are planning to  reach us in the spring.
By David Cooke 29 Oct, 2017
Our first few boats are in a few days ahead of schedule, more are on their way this week before the winter canal stoppages. We would like to thank our moorers for being so patient.
By David Cooke 24 Oct, 2017
We had a positive meeting today with the CRT engineer who confirmed that we have passed all the tests,  we can now connect to the network. We will be opening the entrance on Saturday to accept our first few boats that are currently moored locally or on their way to get to us. We still have lots to do but are planning that all services will be available by the weekend ahead of the scheduled opening. Lookout for the next blog which should include a picture with boats in!


By David Cooke 17 Oct, 2017
We now have boats on the way to get to us by the 30th October. Things are changing daily. Our focus is the short run of pontoons which will accommodate the boats for this winter. You can see the new entrance there is still lots of landscaping and tidying up to do. You can also see our 3 farm geese enjoying the water.
By David Cooke 13 Oct, 2017
It has been a busy week but we have now finished the entrance connection work, just a bit more tidying up to do;  our main contractors have now left the site. We have also passed the first week of leakage testing with CRT and all appears to be ok. There is another CRT check next week and we are expecting to get our signoff from them on 23rd October. There is still lots to do in the next couple of weeks, I'll keep you posted on progress. We are looking forward to welcoming our first boats in the next few weeks.
By David Cooke 02 Oct, 2017
The Marina has been full of water for several weeks, next week we are due to start the stilling test with CRT. We have found out that the traditional way to seal stoplogs is with locomotive ash hence our visit to the local steam engine works where we were allowed to have as much as we wanted. The marina entrance works are progressing on schedule, with the piling to be completed by Tuesday followed by excavation of the entrance later in the week. We are also working on the driveway.

By David Cooke 24 Sep, 2017
We have signed all the paperwork from CRT to connect to the canal, our contractor will be arriving on site tomorrow (25th September) to knock in the entrance piles. This week we have continued with some fencing, finished the pontoon woodwork on the field side, and threaded the electric wires for the mooring bollards. We have had the bulldozer in to restore the field, and a crusher to prepare all the stone for the drive; lots to do, I will update you next week. David
By David Cooke 16 Sep, 2017
We had a productive meeting with the CRT engineers on Thursday,  they have agreed to help us open the marina by 30th October. We have agreed a weekly programme with designers, builders and CRT to ensure everything is in place. This is the news we have been waiting for and gives us a clear target to work to.  I aim to add to the blog each week, this next week we will be finishing the pontoon woodwork, first fix electrics and completing the fencing, the bulldozer is also onsite restoring the field.
By David Cooke 06 Sep, 2017
We have a meeting with CRT (Canal and River Trust) on Thursday 14th September, we hope, to be able to finalise the canal connection. The recent rain is working in our favour. Don't worry the pontoons will be covered with the latest innovative non slip GRP decking that we have imported from China it will only take us an hour and 36 screws to finish each pontoon.
More Posts
Share by: